Tualatin Seeks Input on Rail Crossing Project Options Costing Up to $320 Million
Tualatin residents can weigh three proposed changes to a congested road and rail crossing, plus leaving it unchanged, through an online survey ending September 27.
Tualatin, OR. — The City of Tualatin is asking residents to weigh four options for the intersection of Southwest Tualatin-Sherwood Road and Southwest Boones Ferry Road: build a bridge, lower the road beneath the rail line, widen the existing road, or make no major changes.
The city’s virtual open house runs through September 27. Visitors can review the concepts and complete a survey that the city says takes less than 10 minutes.
The intersection carries drivers, freight traffic, transit riders, pedestrians and cyclists through central Tualatin. According to the city’s study, traffic backs up during peak hours, train crossings interrupt travel, and the existing sidewalks and bike lanes can be uncomfortable to use.
The project team considered 17 alternatives before advancing three for closer review. A no-build option gives the public a way to compare those proposals with leaving the area largely as it is.
| Option | Proposed change | Early cost estimate |
|---|---|---|
| Road over rail | Shift Tualatin-Sherwood Road south and carry it over Boones Ferry Road and the tracks | $135 million–$250 million |
| Road under rail | Shift the road south and lower it beneath Boones Ferry Road and the tracks | $170 million–$320 million |
| Widen at the current crossing | Expand Tualatin-Sherwood Road to three travel lanes in each direction between 89th Avenue and I-5 | $25 million–$60 million |
| No-build | Make no major change to the crossing | No project cost estimate listed |
The estimates are preliminary, expressed in 2030 dollars, and include construction, property purchases, environmental assessment and engineering design.
Either bridge or underpass option would separate road traffic from the rail crossing and is expected to reduce traffic backups. Both would also require property purchases and remove several existing businesses. The underpass would need drainage measures because the lowered road would be in a floodplain.
Widening would cost less and could shorten peak-hour traffic lines, according to the study. Trains would still stop road traffic, however, and the wider street would create a longer crossing for pedestrians and cyclists. The proposal includes wider sidewalks, bike facilities and a separate pedestrian bridge.
The city says it will summarize survey responses for the Planning Commission and City Council. Officials will then use public feedback and the study’s technical findings to identify a preferred option or a smaller group for further study. If the city chooses a bridge or underpass, it estimates that funding, design, property acquisition and permits would take at least seven to 10 years before construction could begin.
Residents can review the plans and respond through the virtual open house and survey.